Galaxy Solar
ERCOT queue ID 27INR0219
| Queue ID | 27INR0219 |
|---|---|
| Project name | Galaxy Solar |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Stainback Switch (bus #) - Elrod Switch (bus #) |
| Point of interconnection | Stainback Switch (bus #2217) - Elrod Switch (bus #3159) |
| County | Ellis |
| State | TX |
| Voltage | Not reported |
| Capacity | 177.3 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2028-10-30 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Galaxy Solar, LLC |
|---|---|
| Cdr Zone | NORTH |
| Fuel Code | SOL |
| Technology Code | PV |
| Screening Study Complete | 45462 |
| Water Availability | Not Required |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.