Substation Scout

Galaxy Solar

ERCOT queue ID 27INR0219

Queue ID27INR0219
Project nameGalaxy Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationStainback Switch (bus #) - Elrod Switch (bus #)
Point of interconnectionStainback Switch (bus #2217) - Elrod Switch (bus #3159)
CountyEllis
StateTX
VoltageNot reported
Capacity177.3 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-10-30
Source datasetlarge

Additional filed fields

Interconnecting EntityGalaxy Solar, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45462
Water AvailabilityNot Required