Galaxy Storage
ERCOT queue ID 27INR0220
Galaxy Storage (27INR0220) is listed in the ERCOT interconnection queue as a 155 MW battery project in Ellis County, TX. The filing names Stainback Switch (bus #) - Elrod Switch (bus #) as its point of interconnection. ERCOT lists its status as “SS Completed, FIS Started, No IA”, with a target commercial operation date of October 30, 2028. It records the screening study as complete on June 19, 2024.
| Queue ID | 27INR0220 |
|---|---|
| Project name | Galaxy Storage |
| Status (as published) | SS Completed, FIS Started, No IA |
| Substation | Stainback Switch (bus #) - Elrod Switch (bus #) |
| Point of interconnection | Stainback Switch (bus #2217) - Elrod Switch (bus #3159) |
| County | Ellis |
| State | TX |
| Voltage | Not reported |
| Capacity | 155 MW |
| Resource (as published) | OTH/BA |
| Resource category | Battery (normalized for filtering) |
| Target commercial operation | 2028-10-30 |
| Source dataset | large |
In ERCOT's status codes, SS is the screening study, FIS the full interconnection study and IA the interconnection agreement.
Same substation and county
Stainback Switch (bus #) - Elrod Switch (bus #) substation: 3 requests in the ERCOT queue, 3 active totaling 431.7 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| 27INR0219 | Galaxy Solar | 177.3 | Solar | SS Completed, FIS Started, No IA |
| 28INR0355 | Galaxy I Solar | 99.4 | Solar | SS Completed, FIS Started, No IA |
Ellis, TX: 30 requests in the ERCOT queue, 26 active totaling 5,761.2 MW.
Tracked changes
No changes to this filing observed since ERCOT tracking began on August 27, 2026. Full change log →
Additional filed fields
| Interconnecting entity | Galaxy Solar, LLC |
|---|---|
| CDR reporting zone | NORTH |
| Fuel code | OTH |
| Technology code | BA |
| Screening study complete | 2024-06-19 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.