Tap Nimbus – Big Onion & Stainback – Elrod Switch DCKT substation interconnection queue
2 active projects totaling 918.9 MW in the ERCOT queue.
2 ERCOT queue filings name Tap Nimbus – Big Onion & Stainback – Elrod Switch DCKT as the point of interconnection, all in Ellis County, TX.
Target commercial operation date as filed: Sep 2030 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: Victory Ellis, LLC (2 filings).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 29INR0264 | Victory Ellis – Gas | 345 | 465.9 | Gas | SS Completed, FIS Started, No IA | Sep 2030 |
| 28INR0529 | Victory Ellis–BESS | 345 | 453 | Battery | SS Completed, FIS Started, No IA | Sep 2030 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Tracked changes at this substation
2 changes to filings at this point of interconnection, observed between weekly snapshots of the ERCOT queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-09-07 | 29INR0264 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
| 2026-09-07 | 28INR0529 | Status change | n/a | SS Started, FIS Started, No IA → SS Completed, FIS Started, No IA |
Other ERCOT queue substations in Ellis County, TX
- Tap Venus - Navarro: 2 active, 663.6 MW of 2 filed
- tap Venus - Navarro: 2 active, 555 MW of 2 filed
- Stainback Switch (bus #) - Elrod Switch (bus #): 3 active, 431.7 MW of 3 filed
- Midlothian ELP: 2 active, 36 MW of 2 filed
- Tap # VENUS_S5 to # NAVARRO: 2 active, 2.8 MW of 2 filed
- Tap Venus Switch - BYNUM_5: 2 active, 2.8 MW of 2 filed