Substation Scout

Galaxy I Solar

ERCOT queue ID 28INR0355

Queue ID28INR0355
Project nameGalaxy I Solar
Status (as published)SS Completed, FIS Started, No IA
SubstationStainback Switch (bus #) - Elrod Switch (bus #)
Point of interconnectionStainback Switch (bus #2217) - Elrod Switch (bus #3159)
CountyEllis
StateTX
VoltageNot reported
Capacity99.4 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-10-30
Source datasetlarge

Additional filed fields

Interconnecting EntityGalaxy Solar, LLC
Cdr ZoneNORTH
Fuel CodeSOL
Technology CodePV
Screening Study Complete45857
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.