Midlothian ELP substation interconnection queue
2 active projects totaling 36 MW in the ERCOT queue.
2 ERCOT queue filings name Midlothian ELP as the point of interconnection, all in Ellis County, TX.
Target commercial operation date as filed: Jun 2028 (2 filings). 2 active filings target a date after November 27, 2026.
Interconnecting entity as filed: MIDLOTHIAN ENERGY, LLC (2 filings).
2active projects
36active MW
2total filed
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| 21INR0534 | Midlothian Unit 2 repower | 345 | 18 | Gas | SS Completed, FIS Started, No IA | Jun 2028 |
| 22INR0543 | Midlothian Unit 3 repower | 345 | 18 | Gas | SS Completed, FIS Started, No IA | Jun 2028 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.
Other ERCOT queue substations in Ellis County, TX
- Tap Nimbus – Big Onion & Stainback – Elrod Switch DCKT: 2 active, 918.9 MW of 2 filed
- Tap Venus - Navarro: 2 active, 663.6 MW of 2 filed
- tap Venus - Navarro: 2 active, 555 MW of 2 filed
- Stainback Switch (bus #) - Elrod Switch (bus #): 3 active, 431.7 MW of 3 filed
- Tap # VENUS_S5 to # NAVARRO: 2 active, 2.8 MW of 2 filed
- Tap Venus Switch - BYNUM_5: 2 active, 2.8 MW of 2 filed
Site Scanner