Substation Scout

Jones, TX interconnection queue

14 active projects totalling 3,780.4 MW in the ERCOT queue, plus 3 with terminal status (shown greyed).

14active projects
3,780.4active MW
17total filed
Queue IDProjectkVMWResourceStatus
30INR0146 Hackberry Draw Solar 345 653 Solar SS Started, FIS Started, No IA
27INR0452 Moccasin Storage 345 603.1 Battery SS Completed, FIS Started, No IA
27INR0065 Funston Solar (AEP POI) n/r 355.2 Solar Inactive
29INR0015 Funston Solar 345 351.1 Solar SS Completed, FIS Completed, IA
23INR0245 Tiger Storage n/r 251 Battery Inactive
29INR0026 Skeeter Solar 345 251 Solar SS Completed, FIS Started, No IA
23INR0244 Tiger Solar 345 250.9 Solar SS Completed, FIS Completed, IA
20INR0241 Crowded Star Solar 345 218.8 Solar SS Completed, FIS Completed, IA
26INR0440 Hamby Solar 138 205.8 Solar SS Completed, FIS Started, IA
25INR0473 Crowded Star I BESS n/r 202.7 Battery SS Completed, FIS Completed, IA
20INR0242 Anson Solar 2 345 200.9 Solar SS Completed, FIS Completed, IA
21INR0247 Anson Solar Center, Phase III 345 200 Solar SS Completed, FIS Started, No IA
22INR0274 Crowded Star Solar II 345 189.5 Solar SS Completed, FIS Completed, IA
22INR0457 Anson BAT 345 153.6 Battery SS Completed, FIS Completed, IA
24INR0378 Solara BESS 1 138 150 Battery SS Completed, FIS Started, No IA
24INR0379 Solara BESS 2 138 150 Battery SS Completed, FIS Started, No IA
24INR0402 Inertia BESS 3 n/r 108.4 Battery Inactive

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.