ERCOT queue ID 22INR0274
| Queue ID | 22INR0274 |
|---|---|
| Project name | Crowded Star Solar II |
| Status (as published) | SS Completed, FIS Completed, IA |
| Substation | tap Claytonville – Phantom Hill c2 (New Substation: Open Sky ) |
| Point of interconnection | tap 345kV 68001 Claytonville – 68004 Phantom Hill c2 (New Substation: Open Sky 68014) |
| County | Jones |
| State | TX |
| Voltage | 345 kV |
| Capacity | 189.5 MW |
| Resource (as published) | SOL/PV |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2026-09-18 |
| Source dataset | large |
Additional filed fields
| Interconnecting Entity | Jones City Solar II, LLC |
|---|---|
| Cdr Zone | WEST |
| Fuel Code | SOL |
| Technology Code | PV |
| Ia Signed | 45134 |
| Screening Study Complete | 43987 |
| Fis Approved | 45601 |
| Air Permit | Not Required |
| Water Availability | Not Required |