Substation Scout

Anson Solar Center, Phase III

ERCOT queue ID 21INR0247

Queue ID21INR0247
Project nameAnson Solar Center, Phase III
Status (as published)SS Completed, FIS Started, No IA
Substationtap WShack - Clayton
Point of interconnectiontap 345kV 68000 WShack - 68001 Clayton
CountyJones
StateTX
Voltage345 kV
Capacity200 MW
Resource (as published)SOL/PV
Resource categorySolar (normalised for filtering)
Target commercial operation2028-06-01
Source datasetlarge

Additional filed fields

Interconnecting EntityAnson Solar Center 3, LLC
Cdr ZoneWEST
Fuel CodeSOL
Technology CodePV
Screening Study Complete42954
Water AvailabilityNot Required

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.