Mountain
Named in 4 PJM planning documents for 5 projects, from March 10, 2026 to November 3, 2026.
Also printed as: Mountain Substation
Same name on other Substation Scout pages
Other sources that print a substation named “Mountain”. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.
Projects naming this substation
Figures are from the most recent document naming each project, as printed. Each links to its page.
| Project | Status as printed | Cost estimate | In-service date | Customer load | As of |
|---|---|---|---|---|---|
| UGI-2022-0001 | Engineering | $6M | 11/2025 | Not printed | 2026-09-08* SRRTEP Mid-Atlantic |
| UGI Utilities: Supplemental UGI-2026-0001 |
Engineering | $94 M | 09/30/2029 | 200MW | 2026-03-10 TEAC |
| UGI-2026-0003 | Engineering | $107.2 M | 03/29/2030 | 500MW | 2026-07-07 TEAC |
| Mountain 230KV Transformer 1 UGI-2026-0004 |
Not printed | Not printed | Not printed | Not printed | 2026-11-03 TEAC |
| Mountain 230KV Transformer 2 UGI-2026-0005 |
Not printed | Not printed | Not printed | Not printed | 2026-11-03 TEAC |
Other substations in these projects
The 5 projects above also name 5 other substations, with what the most recent document says about each.
- Newport Substation UGI New — “construct a new 230/66kV two transformer substation” (p. 6) (in 2 of the 5 projects)
- Hanover UGI Expansion — “Construct a 66kV high side bus at Hanover Substation” (p. 3) (in UGI-2022-0001)
- Hunlock UGI Not stated (in UGI-2022-0001)
- Hunlock Creek Substation UGI, PA Not stated (in UGI Utilities: Supplemental)
- Loomis Substation UGI Work described at it — “Provide an additional networked source to Loomis Substation” (p. 3) (in UGI-2022-0001)
Changes between documents
Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.
| What changed | Printed values | Earlier | Later |
|---|---|---|---|
| In-service date | Q4 of 2027 → 09/30/2029 | 2026-01-15 | 2026-03-10 |
| Substations named | HUNLOCK CREEK → MOUNTAIN; NEWPORT | 2026-01-15 | 2026-03-10 |
| In-service date | Q3 of 2029 and an additional 250MW in Q1 of 2030 → 03/29/2030 | 2026-06-02 | 2026-07-07 |
Every mention
| Date | Document | Project | What the document says about it |
|---|---|---|---|
| 2026-11-03 | TEAC Item 07 - UGI Supplemental Projects - Presentation p. 3 |
Mountain 230KV Transformer 1 | “The Mountain #1 230/66kV transformer is approximately 54 years old, has been degrading in testing” 230KV |
| 2026-11-03 | TEAC Item 07 - UGI Supplemental Projects - Presentation p. 4 |
Mountain 230KV Transformer 2 | “The Mountain #2 230/66kV transformer is approximately 54 years old, has been degrading in testing” 230KV |
| 2026-09-08* | SRRTEP Mid-Atlantic UGI local plan submission for 2024 RTEP p. 2 |
UGI-2022-0001 | No role wording 66kV |
| 2026-07-07 | TEAC Item 04 - UGI Supplemental Projects p. 4 |
UGI-2026-0003 | “Mountain Substation 230kV High-Side Improvement: Adds 230kV bus tie breakers as well as two line breakers.” 230kV |
| 2026-03-10 | TEAC Item 04 - UGI Supplemental Projects p. 6 |
UGI Utilities: Supplemental | “An upgrade to the 66kV bus at Mountain Substation is needed” 66kV |
* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.
Before relying on any of this
- Names are machine-extracted from PDFs by a language model. Every exported name was checked to be printed in the PDF text; names read only from maps or diagrams are excluded.
- An entry is a name within a transmission zone, not a verified physical facility. The same name in two zones is two entries; spelling variants are merged only when they differ by punctuation, case or a generic suffix such as "Substation", or when a PJM document prints a rename for the same project (src/ingest/rtepAliases.json; the entry lists its old names).
- role is "new" only where a cited document phrase calls the substation new, describes constructing it, or calls it proposed (graded by src/lib/roleBasis.js), "existing" where a phrase describes work at it, otherwise "unknown".
- expansion is set on a substation that is not "new" where a cited phrase describes a new voltage level, a new or expanded yard, bus or bay, or a named load connected to it (graded by src/lib/expansionBasis.js). It reproduces what the document describes and adds nothing to it.
- Costs, dates, statuses and loads are the documents' own printed values for the most recent document that names the substation. Each one shipped here is printed on its cited page ("verification": "exact" or "on-page"); values that failed that check are withheld and counted in figures_withheld_unverified. None has been reviewed by a person.
- Zone is the transmission owner whose deck presented the project. PJM-SYSTEM marks names from PJM's own reliability decks, which span zones.
- A printed customer load is the amount a document states for a request. It says nothing about the substation's capability.