Newport Substation

Named in 2 PJM planning documents for 2 projects, from March 10, 2026 to July 7, 2026.

Newdescribed as
UGIzone
230/66kV, 230kVkV as printed
2mentions

Described as new: “construct a new 230/66kV two transformer substation” — source, page 6

Also printed as: Newport Switching Station

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
UGI Utilities: Supplemental
UGI-2026-0001
Engineering $94 M 09/30/2029 200MW 2026-03-10
TEAC
UGI-2026-0003 Engineering $107.2 M 03/29/2030 500MW 2026-07-07
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date Q4 of 2027 → 09/30/2029 2026-01-15 2026-03-10
Substations named HUNLOCK CREEK → MOUNTAIN; NEWPORT 2026-01-15 2026-03-10
In-service date Q3 of 2029 and an additional 250MW in Q1 of 2030 → 03/29/2030 2026-06-02 2026-07-07

Every mention

DateDocumentProjectWhat the document says about it
2026-07-07 TEAC
Item 04 - UGI Supplemental Projects p. 4
UGI-2026-0003 No role wording
230kV
2026-03-10 TEAC
Item 04 - UGI Supplemental Projects p. 6
UGI Utilities: Supplemental “construct a new 230/66kV two transformer substation”
230/66kV