Substation Scout

Brunner Island

Named in 2 PJM planning documents for 2 projects, from April 7, 2026 to September 8, 2026.

Not stateddescribed as
PPLzone
230 kV, 230kVkV as printed
2mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
PPL Transmission Zone: Baseline
b3774
Not printed $4.3M 6/1/2027 Not printed 2026-04-07
TEAC
Bressler 230kV Switchyard
PPL-2026-0037
Conceptual $169 M 03/31/2029 900 MW 2026-09-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Cost estimate
prior value printed on the same page
$2.5 M → $4.3M 2026-04-07 2026-04-07
In-service date 03/2029 → 03/31/2029 2026-06-02 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08 TEAC
Item 07 - PPL Supplemental Projects p. 10
Bressler 230kV Switchyard No role wording
230kV
2026-04-07 TEAC
Item 11 - Reliability Analysis Update p. 11
PPL Transmission Zone: Baseline No role wording
230 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this