Bressler 230kV Switchyard

Named in 1 PJM planning document for 1 project, on September 8, 2026.

Newdescribed as
PPLzone
230kVkV as printed
1mentions

Described as new: “terminate at the new Bressler 230kV switchyard” — source, page 8

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Bressler 230kV Switchyard
PPL-2026-0037
Conceptual $169 M 03/31/2029 900 MW 2026-09-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 03/2029 → 03/31/2029 2026-06-02 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08 TEAC
Item 07 - PPL Supplemental Projects p. 8
Bressler 230kV Switchyard “terminate at the new Bressler 230kV switchyard”
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this