Steelton

Named in 4 PJM planning documents for 2 projects, from June 5, 2025 to October 6, 2026.

Existingdescribed as
PPLzone
230kVkV as printed
4mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Highspire, PA
PPL-2025-0007
Conceptual $89 M 05/30/2028 450 MW 2026-10-06
TEAC
Bressler 230kV Switchyard
PPL-2026-0037
Conceptual $169 M 03/31/2029 900 MW 2026-09-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
In-service date 09/2027 → 05/30/2028 2025-05-06 2025-06-05
In-service date 03/2029 → 03/31/2029 2026-06-02 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - PPL Local Plan Submission of the Supplemental Projects for 2026 p. 19
Highspire, PA No role wording
2026-09-17* SRRTEP Mid-Atlantic
PPL local plan submission for 2026 RTEP p. 19
Highspire, PA No role wording
230kV
2026-09-08 TEAC
Item 07 - PPL Supplemental Projects p. 9
Bressler 230kV Switchyard “Switchyard will be retired as the bus and bay conductor limit the line ratings.”
230kV
2025-06-05 TEAC
Item 05 - PPL Supplemental Projects p. 8
Highspire, PA No role wording
230kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.