Mountaineer substation interconnection queue

3 active projects totalling 66 MW in the PJM queue, plus 1 with terminal status (shown greyed).

3active projects
66active MW
4total filed
Queue IDProjectkVMWResourceStatus
N41 Mountaineer 765kV 765 1,200 Coal Withdrawn
AB1-109 Mountaineer #1 n/r 36 Coal Partially in Service - Under Construction
O32 Mountaineer #1 765 20 Coal In Service
C01-1215 Mountaineer 765 kV 765 10 Coal Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.