Monroe

Named in 4 PJM planning documents for 4 projects, from October 8, 2024 to November 13, 2025.

Existingdescribed as
JCPLzone
34.5 kVkV as printed
5mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Jamesburg – Monroe 34.5 kV Line
b4016.1
Not printed $6.35 M 6/1/2030 Not printed 2025-11-13
SRRTEP Mid-Atlantic
Jamesburg – Monroe 34.5 kV Line Not printed $6.35 M 6/1/2030 Not printed 2025-10-16
SRRTEP Mid-Atlantic
Costco – Monroe 34.5 kV
JCPL-2022-001 · s2840
Not printed $1.3M 11/17/2022 13.9 MW 2026-09-08*
SRRTEP Mid-Atlantic
Automatic Restoration Projects
JCPL-2023-008 · s3234.1
Not printed $1.89 12/31/2024 Not printed 2024-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 110
Costco – Monroe 34.5 kV “from the Monroe substation”
34.5 kV
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 13
Automatic Restoration Projects “At Monroe, replace relaying”
34.5 kV
2025-11-13 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 27
Jamesburg – Monroe 34.5 kV Line “revise relay settings at Monroe Substation”
2025-10-16 SRRTEP Mid-Atlantic
Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 27
Jamesburg – Monroe 34.5 kV Line “Replace limiting conductor and revise relay settings at Monroe Substation”
34.5 kV
2024-10-08 TEAC
Informational Only - JCPL Local Plan submission of supplemental project 2024 p. 13
Automatic Restoration Projects “At Monroe, replace relaying”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.