Jamesburg

Named in 3 PJM planning documents for 3 projects, from October 16, 2025 to November 13, 2025.

Existingdescribed as
JCPLzone
34. 5 kV, 34.5 kVkV as printed
3mentions

Also printed as: Jamesburg Substation

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Jamesburg – Monroe 34.5 kV Line
b4016.1
Not printed $6.35 M 6/1/2030 Not printed 2025-11-13
SRRTEP Mid-Atlantic
Jamesburg – Monroe 34.5 kV Line Not printed $6.35 M 6/1/2030 Not printed 2025-10-16
SRRTEP Mid-Atlantic
Costco – Monroe 34.5 kV
JCPL-2022-001 · s2840
Not printed $1.3M 11/17/2022 13.9 MW 2026-09-08*
SRRTEP Mid-Atlantic

Every mention

DateDocumentProjectWhat the document says about it
2026-09-08* SRRTEP Mid-Atlantic
JCPL local plan submission for 2024 RTEP p. 110
Costco – Monroe 34.5 kV No role wording
34. 5 kV
2025-11-13 SRRTEP Mid-Atlantic
Item 01 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 27
Jamesburg – Monroe 34.5 kV Line No role wording
2025-10-16 SRRTEP Mid-Atlantic
Item 02 - SRRTEP Mid-Atlantic - Reliability Analysis Update p. 27
Jamesburg – Monroe 34.5 kV Line “Rebuild the Jamesburg - Monroe 34.5 kV N40 Line from Jamesburg Substation”
34.5 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this