Villa Rica

Named in 7 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
7projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
GTC: HICKORY LEVEL - VILLA RICA 230kV LINE RECONDUCTOR
Reconductor 8.6 miles Hickory Level - Villa Rica 230kV line with 160C 1351 ACSS and replace the 230kV line trap at Villa Rica
TEAMS 19635 · plan p.117 · zone 211
GTC In the plan
p.10
May 1, 2027 No change Hickory Level, Villa Rica
CC - GARRETT ROAD 230kV SS (NETWORK IMPROVEMENTS)
Build the new Garrett Road 230kV switching station splitting the Villa Rica - West Marietta 230kV line. Build a new 230kV line from the Trae Lane substation to the Garrett Road switching substation with bundled 100C 1351 ACSR conductor.
TEAMS 20243 · plan p.115 · zone 201
GPC In the plan
p.9
Dec 31, 2026 Delayed within 2026 Garrett Road, Trae Lane, Villa Rica, West Marietta
GTC: GARRETT RD - V. RICA 230kV LINE RECONDUCTOR NETWORK IMPROV
Reconductor the section from East Villa Rica Switching station to Garrett Rd with 160C 1351 ACSS on 11.5 miles of the Garrett Road - Villa Rica 230kV line. Additionally, the 2.5 miles section from East Villa Rica Switching Station to Villa Rica will be rebuilt with bundled 200C 1351 ACSS Martin.
TEAMS 20505 · plan p.131 · zone 201
GTC In the plan
p.11
Jun 1, 2027 No change East Villa Rica, GARRETT RD, Garrett Road, RICA, Villa Rica
GTC: DOUGLASVILLE - VILLA RICA 230kV REBUILD (CC NET IMPRVT)
Rebuild a 2.5 miles section of the Villa Rica - Douglasville 230kV line with bundled 200C 1351 ACSS Martin conductor.
TEAMS 20776 · plan p.127 · zone 201
GTC In the plan
p.10
Jun 1, 2027 No change Douglasville, Villa Rica
CC - SUMMER LAKE - VILLA RICA 230kV REBUILD (IMPROVEMENTS)
Rebuild a 2.5 miles portion of the Summer Lake - Villa Rica 230kV line with bundled 200C 1351 ACSS Martin.
TEAMS 20781 · plan p.124 · zone 201
GPC In the plan
p.10
Jun 1, 2027 No change Summer Lake, Villa Rica
GTC: CAVENDER DRIVE 500/230kV AUTO TRANSFORMER
Cavender Drive will become a 500/230kV station looping in the Villa Rica - Union City 500kV line and installing a 500/230kV auto transformer.
TEAMS 21013 · plan p.246 · zone 201
GTC In the plan
p.18
Jun 1, 2030 No change Union City, Villa Rica
SMART VALVES AT EAST VILLA RICA SWITCHING STATION
Install Advanced Power Flow Controllers at the new East Villa Rica Switching Station on the Douglasville - Villa Rica 230kV and Summer Lake - Villa Rica 230kV lines.
TEAMS 21069 · plan p.184 · zone 201
GPC In the plan
p.14
Jun 1, 2028 No change Douglasville, East Villa Rica, Summer Lake, Villa Rica

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.