Named in 8 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
8projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| POSSUM BRANCH - YATES COMMON 115kV REBUILD (YATES TO CLEM) Rebuild approximately 11 miles section of the Possum Branch - Yates 115kV line and replace limiting elements along the line with a higher rating. TEAMS 15879 · plan p.218 · zone 211 |
GPC | In the plan p.16 |
Jun 1, 2029 | Delayed from 2027 to 2029 | Possum Branch, Yates, Yates Common |
| UNION CITY - YATES 230kV (WHITE) LINE REBUILD Rebuild 23.4 miles of the Union City - Yates 230kV (White) line with bundled 200C 1351 ACSS Martin conductor. TEAMS 17900 · plan p.107 · zone 208 |
GPC | In the plan p.9 |
Jun 1, 2026 | No change | Union City, Yates |
| CC - SHUGART (NETWORK IMPROVEMENTS) GPC will rebuild and reconfigure the Line Creek 230kV substation and connect the Morrow - Yates 230kV line and the Union City - Yates 230kV White and Black lines into Line Creek. Build two short lines from Line Creek to Shugart Farms (0.3 miles each) with 100C 1351 ACSR Martin conductor. TEAMS 18736 · plan p.123 · zone 208 |
GPC | In the plan p.10 |
Jun 1, 2027 | No change | Morrow, Union City, Yates |
| UNION CITY - YATES 230kV (BLACK) LINE REBUILD Rebuild the Union City - Yates 230kV (Black) line with bundled 200C 795 ACSS Martin conductor. Replace limiting elements at Union City, Fairburn #1 and Line Creek substations. TEAMS 20274 · plan p.185 · zone 208 |
GPC | In the plan p.14 |
Jun 1, 2028 | No change | Union City, Yates |
| UNION CITY - YATES 230kV (WHITE) SWITCH AND TRAP REPLACEMENT Replace the limiting elements at Union City and Yates substations along the Union City - Yates 230kV (White) line. TEAMS 20691 · plan p.108 · zone 208 |
GPC | In the plan p.9 |
Jun 1, 2026 | No change | Union City, Yates |
| GTC: YATES - LINE CREEK 230kV (GREEN) REBUILD Rebuild 16.5 miles of the Yates - Line Creek (Green) 230kV line using 200C 1351 ACSS Martin. TEAMS 21298 · plan p.255 · zone 208 |
GTC | In the plan p.19 |
Jun 1, 2030 | New project | Yates |
| GTC: YATES - LINE CREEK 230kV (RED) REBUILD Rebuild 16.5 miles of the Yates - Line Creek (Red) 230kV line using 200C 1351 ACSS Martin. TEAMS 21321 · plan p.256 · zone 208 |
GTC | In the plan p.19 |
Jun 1, 2030 | New project | Yates |
| GTC: DRESDEN JUMPER REPLACEMENT Replace the jumpers at Dresden limiting the Dresden - Yates 230kV line with higher rated jumpers. TEAMS 21626 · plan p.277 · zone 208 |
GTC | In the plan p.20 |
Jun 1, 2031 | New project | Dresden, Yates |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.
Site Scanner