Morrow

Named in 9 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
9projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
CC - SHUGART (NETWORK IMPROVEMENTS)
GPC will rebuild and reconfigure the Line Creek 230kV substation and connect the Morrow - Yates 230kV line and the Union City - Yates 230kV White and Black lines into Line Creek. Build two short lines from Line Creek to Shugart Farms (0.3 miles each) with 100C 1351 ACSR Martin conductor.
TEAMS 18736 · plan p.123 · zone 208
GPC In the plan
p.10
Jun 1, 2027 No change Morrow, Union City, Yates
MORROW - MOUNTAIN VIEW 115 kV REBUILD
Rebuild the 1.7 miles Mountain View - Barnett Road section of the Morrow - Mountain View 115kV line with 200C 1351 ACSS Martin conductor.
TEAMS 19363 · plan p.116 · zone 208
GPC In the plan
p.9
Dec 31, 2026 No change Morrow, Mountain View
MORROW - YATES COMMON 115kV LINE REBUILD
On the Fife - Fairburn SW - Line Creek sections of the Morrow - Yates Common 115kV line, rebuild approximately 5.1 miles with 200C 1351 ACSS Martin.
TEAMS 19601 · plan p.118 · zone 208
GPC In the plan
p.10
May 1, 2027 No change Morrow, Yates Common
CC - TA REALTY ELLENWOOD NETWORK IMPROVEMENTS
Rebuild and Reconductor the Austin Drive - Morrow 115kV line. Rebuild with 200C 1351 ACSS Martin on the Austin Drive - Rainbow Drive section. Reconductor with 180C 973 ACCS between Rainbow Drive - River Road - Williamson Road and 180C 1780 ACCS between Williamson Road - Ellenwood - Morrow. At Austin Drive 115kV, replace the 230/115kV auto transformer along with upgrades of other limiting elements at the station. Remo…
TEAMS 20736 · plan p.125 · zone 208
GPC In the plan
p.10
Jun 1, 2027 No change Austin Drive, Morrow
CC - GULLATT ROAD TRANSMISSION IMPROVEMENTS
Rebuild the Morrow - Yates Common 115kV line from Line Creek to the new Gullatt Road substation. Rebuild the Line Creek - Fairburn #2 115kV line from Line Creek to the new Gullatt Road substation. Remove the Owens Corning Tap Connection on the Morrow - Yates Common 115kV line and rebuild the line from North Coweta to Str 1. Build new line section from Str 1 to the new Gullatt Road substation. All rebuilds will be don…
TEAMS 20771 · plan p.120 · zone 208
GPC In the plan
p.10
Jun 1, 2027 No change Fairburn, Gullatt Road, Morrow, Yates Common
GRADY - MORROW (WHITE) 115kV REBUILD
Rebuild 1.76 miles of line from Grady - Moreland Way with 200C 1351 ACSS conductor. Rebuild 3.5 miles of line from Fayetteville Rd Jct - Conley Creek Jct with 200C 1351 ACSS conductor.
TEAMS 21139 · plan p.197 · zone 206
GPC In the plan
p.15
Jun 1, 2029 Delayed from 2026 to 2029 GRADY, Morrow
EAST POINT - MORROW 115kV REBUILD
Rebuild a 3 miles section of the East Point - Morrow 115kV line, 1.4 mile from East Point to College Point Tap and 1.5 mile from Morrow to Forest Park with 200C 1351 ACSS Martin. Also rebuild portions of Morrow - Mountain View and East Point - Mountain View 115kV lines.
TEAMS 21303 · plan p.306 · zone 208
GPC In the plan
p.22
Jun 1, 2035 New project East Point, Morrow, Mountain View
JONESBORO - MORROW RELAY PROTECTION UPGRADE
Upgrade the Jonesboro - Morrow 115kV line relay protection schemes.
TEAMS 21573 · plan p.58 · zone 208
GPC In the plan
p.9
Mar 1, 2027 New Project Jonesboro, Morrow
EAST POINT - MORROW 115kV LIMITING ELEMENTS REMOVAL
Remove limiting elements at the substation terminals for the East Point - Morrow 115kV lines. This involves upgrading associated switches and jumpers with higher rated equipment.
TEAMS 21628 · plan p.195 · zone 208
GPC In the plan
p.15
Jun 1, 2029 New project East Point, Morrow

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.