Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
BOWEN-BRANDON FARM RD 230kV REBUILD
Rebuild the 0.05 mile section outside Bowen on the Bowen - Pegamore 230kV line and replace limiting elements.
TEAMS 16903 · plan p.231 · zone 211
GPC In the plan
p.17
Jun 1, 2030 New project Bowen, Pegamore
CC - VILLA RICA UPGRADES (NETWORK IMPROVEMENTS)
Add a new 500/230kV auto transformer at Villa Rica, and loop in and out the Bowen - Union City 500kV line into Villa Rica. Reconfigure the 230kV yard.
TEAMS 20774 · plan p.158 · zone 211
GPC In the plan
p.12
Jun 1, 2028 No change Bowen, Union City
BOWEN - JUDY MOUNTAIN 230kV REBUILD
Rebuild the Bowen - Judy Mountain 230kV line, 32.79 miles, with (2) 200C 1351 ACSS Martin conductor.
TEAMS 21497 · plan p.230 · zone 211
GPC In the plan
p.17
Jun 1, 2030 New project Bowen, Judy Mountain

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.