Substation Scout

Aquia Harbour

Named in 1 PJM planning document for 1 project, on October 8, 2025.

Existingdescribed as
DOMzone
—kV as printed
1mentions

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Fredericksburg to Possum Corridor – Add 3rd and 4th 230kV Lines
DOM-2024-0035 · s3701
Conceptual $180.0M 06/01/2029 Not printed 2025-10-08
TEAC

Every mention

DateDocumentProjectWhat the document says about it
2025-10-08 TEAC
Informational Only - Dominion Local Plan Submission of the Supplemental Projects 2025 p. 8
Fredericksburg to Possum Corridor – Add 3rd and 4th 230kV Lines “from Fredericksburg to Aquia Harbour”

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.