Miami Fort

Named in 8 PJM planning documents for 3 projects, from December 13, 2024 to October 6, 2026.

Existingdescribed as
DEOKzone
138 kV, 345 kVkV as printed
8mentions

PJM interconnection queue

A PJM queue substation page has the same name: Miami Fort (OH) — 3 queue requests filed, 1 active.

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Projects naming this substation

Figures are from the most recent document naming each project, as printed. Each links to its page.

ProjectStatus as printedCost estimateIn-service dateCustomer loadAs of
Miami Fort – Clifty Creek
DEOK-2023-001 · s3598.1
Engineering $39.0 MM 12/31/2026 Not printed 2025-10-08
TEAC
Sutton Ridge-Miami Fort
DEOK-2024-008 · s3806.1
Conceptual $5.3M 6/1/2032 Not printed 2026-10-06
TEAC
Customer Load Request
DEOK-2025-003
Not printed Not printed Not printed 800 MW 2026-09-08
TEAC

Changes between documents

Where two documents print different values for the same project. A large change in a cost estimate can reflect a need being combined with others into one solution, not only a re-estimate; read both pages.

What changedPrinted valuesEarlierLater
Substations named MIAMI FORT; SUTTON RIDGE → GREENDALE; MIAMI FORT; SUTTON RIDGE 2024-12-13 2025-03-14
Substations named BECKETT; COTTON RUN; MIAMI FORT; MILLIKIN; PORT UNION; TODHUNTER; WAYNE MADISON; WEST MILTON; WOODSDALE → BECKETT; COTTON RUN; MIAMI FORT; MILLIKIN; MORGAN; PORT UNION; TODHUNTER; WAYNE MADISON; WEST MILTON; WILLEY; WOODSDALE 2025-07-08 2026-09-08

Every mention

DateDocumentProjectWhat the document says about it
2026-10-06 TEAC
Informational Only - DEOK Local Plan Submission of the supplemental projects for 2026 p. 5
Sutton Ridge-Miami Fort “sections between Miami Fort substation and the Ohio/Indiana State border”
138 kV
2026-09-30* SRRTEP Western
DEOK local plan submission of the supplemental projects for 2026 RTEP p. 5
Sutton Ridge-Miami Fort “line work is limited to sections between Miami Fort substation and the Ohio/Indiana State border”
138 kV
2026-09-08 TEAC
Item 08 - DEOK Supplemental Projects p. 4
Customer Load Request “existing Miami Fort to Woodsdale 345 kV circuit”
345 kV
2026-09-08* SRRTEP Western
DEOK local plan submission of the supplemental projects for 2025 RTEP p. 2
Miami Fort – Clifty Creek “The protection at Miami Fort failed to operate”
2025-10-08 TEAC
Informational Only - DEOK Local Plan Submission of the Supplemental Projects for 2025 p. 2
Miami Fort – Clifty Creek No role wording
2025-07-08 TEAC
Item 08 - DEOK Supplemental Projects p. 4
Customer Load Request No role wording
345 kV
2025-03-14 SRRTEP Western
Item 06 - DEOK Supplemental Projects p. 9
Sutton Ridge-Miami Fort “A new 138 kV breaker position at Miami Fort”
138 kV
2024-12-13 SRRTEP Western
Item 14 - DEOK Supplemental Projects p. 3
Sutton Ridge-Miami Fort “new 138 kV breaker position at Miami Fort”
138 kV

* A local-plan posting carries no meeting date; the date shown is when pjm.com last modified the file.

Before relying on any of this