Substation Scout

Twin Branch - Argenta 345 kV

PJM queue ID C01-1203

Twin Branch - Argenta 345 kV (C01-1203) is listed in the PJM interconnection queue as a 184 MW solar project in Cass County, MI. The filing names Twin Branch - Argenta as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2030.

Queue IDC01-1203
Project nameTwin Branch - Argenta 345 kV
Status (as published)Active
SubstationTwin Branch - Argenta
Point of interconnectionTwin Branch - Argenta 345 kV
CountyCass
StateMI
Voltage345 kV
Capacity184 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2030-12-31
Source datasetcycle

Same substation and county

Twin Branch - Argenta substation: 2 requests in the PJM queue, 2 active totaling 384 MW.

Queue IDProjectMWResourceStatus
C01-1409Twin Branch - Argenta 345 kV200BatteryActive

Cass, MI: 20 requests in the PJM queue, 7 active totaling 1,778.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperBair Lake Power, LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy200.0
MW capacity184.0
MFO200.0
Submitted date4/27/2026
Last updated10/1/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first