Penns-Richfield Tie #1 substation interconnection queue

2 active projects totaling 36 MW in the PJM queue.

2 PJM queue filings name Penns-Richfield Tie #1 as the point of interconnection, all in Snyder County, PA.

Target commercial operation date as filed: Dec 2027 (2 filings). 2 active filings target a date after November 27, 2026.

2active projects
36active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AF2-234 Washington West Solar 69 24 Hybrid Under Construction Dec 2027
AF2-233 Washington East Solar 69 12 Hybrid Under Construction Dec 2027

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Snyder County, PA

All 26 PJM queue filings in Snyder County, PA.