Pantago-Five Points substation interconnection queue

1 active project totalling 39 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
39active MW
2total filed
Queue IDProjectkVMWResourceStatus
AB2-169 Wilkinson Solar Energy Center 115 39 Solar In Service
AI2-272 Pantago-Five Points 115kV 115 32.6 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.