Substation Scout

Page-Bethel substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
AD1-083 Cape Solar 138 60.1 Solar Withdrawn
AG2-145 Page-Bethel 138 kV 138 0 Hybrid Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.