Substation Scout

Pulaski, VA interconnection queue

4 active projects totalling 152.1 MW in the PJM queue, plus 23 with terminal status (shown greyed).

4active projects
152.1active MW
27total filed
Queue IDProjectkVMWResourceStatus
AF2-106 Pulaski Solar 138 90 Solar Engineering and Procurement
AI2-216 Wurno - Claytor lake 138 kV 138 77 Wind Withdrawn
AD2-178 Blackbird Solar 138 72 Solar Withdrawn
AD2-179 Blue Jay Solar 138 60 Solar Withdrawn
AF2-105 Bella Terra 138 60 Solar Withdrawn
AH1-269 Claytor 138 kV 138 50 Battery Active
AG1-091 Hickman-River Bend 69 kV 69 32.4 Solar Withdrawn
AD2-201A Hickman-Riverbend 69kV 69 31 Solar Withdrawn
AC1-226 Wurno-Claytor 138kV 138 26 Wind Withdrawn
AD1-102 Wurno-Claytor Lake 138 KV 138 23.4 Wind Withdrawn
Z2-042 Wurno-Clayor 138kV 138 23.3 Wind Withdrawn
AC2-002 Not reported n/r 23 Wind Withdrawn
AC1-156 Morgan's Cut 34.5kV 34.5 22.8 Solar Withdrawn
AF2-220 Hickman-River Bend 69 kV 69 22.2 Solar Withdrawn
AC2-096 Wurno I 34.5KV 34.5 12 Solar Withdrawn
AC2-097 Wurno II 34.5kV 34.5 12 Solar Withdrawn
AH1-379 Hickman 69 kV 69 12 Solar Withdrawn
AE1-017 Peak Creek-Draper 34.5 kV 34.5 11 Solar Withdrawn
W3-021 Jacksons Ferry-Peak Creek 138kV 138 9.1 Wind Withdrawn
AH1-182 Peak Creek 34.5 n/r 6.9 Solar Withdrawn
C01-1663 Claytor 138 kV 138 6.1 Hydro Active
X2-040 Wurno 34.5kV 34.5 6 Gas Withdrawn
Y1-049 New River Resource Authority Waste Management Facility IRD LEG-E 34.5 6 Gas In Service
AE1-018 Pulaski Community Solar 12 2.8 Solar Withdrawn
AG1-092 Hickman-River Bend 69 kV 69 0 Battery Withdrawn
AG2-145 Page-Bethel 138 kV 138 0 Hybrid Withdrawn
AG2-273 Wurno 138 kV 138 0 Battery Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.