Olive - Reynolds #2 345 kV
PJM queue ID C01-2035
Olive - Reynolds #2 345 kV (C01-2035) is listed in the PJM interconnection queue as a 18.2 MW solar project in Pulaski County, IN. The filing names Olive - Reynolds #2 as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2028.
| Queue ID | C01-2035 |
|---|---|
| Project name | Olive - Reynolds #2 345 kV |
| Status (as published) | Active |
| Substation | Olive - Reynolds #2 |
| Point of interconnection | Olive - Reynolds #2 345 kV |
| County | Pulaski |
| State | IN |
| Voltage | 345 kV |
| Capacity | 18.2 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2028-12-31 |
| Source dataset | cycle |
Same substation and county
Olive - Reynolds #2 substation: 2 requests in the PJM queue, 2 active totaling 96.2 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AH1-482 | Olive - Reynolds #2 345 kV | 78 | Battery | Active |
Pulaski, IN: 21 requests in the PJM queue, 11 active totaling 1,270.9 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Mayapple Solar, LLC |
|---|---|
| Transmission owner | AEP |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 0.0 |
| MW capacity | 18.2 |
| MFO | 338.0 |
| Submitted date | 4/27/2026 |
| Last updated | 6/5/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.