Marion County substation interconnection queue

1 active project totalling 64.2 MW in the PJM queue, plus 2 with terminal status (shown greyed).

1active projects
64.2active MW
3total filed
Queue IDProjectkVMWResourceStatus
AF1-116 Marion County 161 kV 161 72 Solar Withdrawn
AE1-143 Northern Bobwhite Solar 161 64.2 Solar Under Construction
AI2-066 Marion County 161 kV 161 16.4 Solar Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.