Marion, KY interconnection queue
2 active projects totalling 87.5 MW in the PJM queue, plus 6 with terminal status (shown greyed).
2active projects
87.5active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AE1-143 | Northern Bobwhite Solar | 161 | 64.2 | Solar | Under Construction |
| AG1-488 | Marion Co 161 kV | 161 | 42 | Solar | Withdrawn |
| AG2-298 | Sulphur Creek-Loretto 69 kV | 69 | 23.3 | Solar | Active |
| AH1-532 | Marion County - Marion Co. Industrial 161 kV | 161 | 22.7 | Solar | Withdrawn |
| AI2-066 | Marion County 161 kV | 161 | 16.4 | Solar | Withdrawn |
| AH2-263 | Marion Co - Marion Co industrial 161 kV | 161 | 15.5 | Solar | Withdrawn |
| AG2-512 | Sulphur Creek-Loretto 69 kV | 69 | 11 | Solar | Withdrawn |
| AI2-349 | Loretto 69 kV | 69 | 11 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.