Substation Scout

Jacksons Ferry substation interconnection queue

2 active projects totalling 75.9 MW in the PJM queue.

2active projects
75.9active MW
2total filed
Queue IDProjectkVMWResourceStatus
AC2-123 Wythe County Solar Project 138 44.6 Solar In Service
AE2-326 Wythe County Solar Project 138 31.3 Battery Engineering and Procurement

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.