Substation Scout

Jacksons Ferry substation interconnection queue

2 active projects totaling 75.9 MW in the PJM queue.

2 PJM queue filings name Jacksons Ferry as the point of interconnection, all in Wythe County, VA.

Target commercial operation dates as filed run from Mar 2025 to Jun 2028 (2 filings). 1 active filing targets a date after November 27, 2026.

2active projects
75.9active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AC2-123 Wythe County Solar Project 138 44.6 Solar In Service Mar 2025
AE2-326 Wythe County Solar Project 138 31.3 Battery Engineering and Procurement Jun 2028

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Same name on other Substation Scout pages

Other sources that print a substation named “Jacksons Ferry” in VA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.

Other PJM queue substations in Wythe County, VA

All 11 PJM queue filings in Wythe County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first