Substation Scout

Mount Airy - Wythe substation interconnection queue

1 active project totaling 110.6 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Mount Airy - Wythe as the point of interconnection, all in Wythe County, VA.

Target commercial operation dates as filed run from Dec 2023 to Dec 2029 (2 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: AEP (1 filing).

1active projects
110.6active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-1984 Mount Airy - Wythe 138 kV 138 110.6 Solar Active Dec 2029
AG2-432 Mount Airy - Wythe 138 kV 138 30 Solar Withdrawn Dec 2023

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Wythe County, VA

All 11 PJM queue filings in Wythe County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first