Wythe County Solar Project

PJM queue ID AE2-326

Queue IDAE2-326
Project nameWythe County Solar Project
Status (as published)Engineering and Procurement
SubstationJacksons Ferry
Point of interconnectionJacksons Ferry 138 kV
CountyWythe
StateVA
Voltage138 kV
Capacity31.3 MW
Resource (as published)Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2028-06-15
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy52.2
Mw Capacity31.32
Mfo127.2

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.