Wythe County Solar Project

PJM queue ID AE2-326

Wythe County Solar Project (AE2-326) is listed in the PJM interconnection queue as a 31.3 MW battery project in Wythe County, VA. The filing names Jacksons Ferry as its point of interconnection. PJM lists its status as “Engineering and Procurement”, with a target commercial operation date of June 15, 2028.

Queue IDAE2-326
Project nameWythe County Solar Project
Status (as published)Engineering and Procurement
SubstationJacksons Ferry
Point of interconnectionJacksons Ferry 138 kV
CountyWythe
StateVA
Voltage138 kV
Capacity31.3 MW
Resource (as published)Storage
Resource categoryBattery (normalized for filtering)
Target commercial operation2028-06-15
Source datasetserial

Same substation and county

Jacksons Ferry substation: 2 requests in the PJM queue, 2 active totaling 75.9 MW.

Queue IDProjectMWResourceStatus
AC2-123Wythe County Solar Project44.6SolarIn Service

Wythe, VA: 11 requests in the PJM queue, 4 active totaling 486.5 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy52.2
MW capacity31.32
MFO127.2

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first