Hanging Rock CC2 (T73) is listed in the PJM interconnection queue as a 20 MW gas project in Lawrence County, OH. The filing names Hanging Rock as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of June 1, 2008.

Queue IDT73
Project nameHanging Rock CC2
Status (as published)In Service
SubstationHanging Rock
Point of interconnectionHanging Rock 765kV
CountyLawrence
StateOH
Voltage765 kV
Capacity20 MW
Resource (as published)Natural Gas
Resource categoryGas (normalized for filtering)
Target commercial operation2008-06-01
Source datasetserial

Same substation and county

Hanging Rock substation: 5 requests in the PJM queue, 3 active totaling 51 MW.

Queue IDProjectMWResourceStatus
AH1-686Hanging Rock 765 kV21GasActive
AA1-013Cornu10GasIn Service
X1-027Hanging Rock 138kV200CoalWithdrawn
Y3-096Hanging Rock 765kV0BatteryWithdrawn

Lawrence, OH: 8 requests in the PJM queue, 5 active totaling 141 MW.

A substation with the same name is named in PJM transmission planning materials: Hanging Rock (AEP, 4 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy20
MW capacity20
MFO1240

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first