1 active project totalling 75 MW in the PJM queue, plus 1 with terminal status (shown greyed).

1active projects
75active MW
2total filed
Queue IDProjectkVMWResourceStatus
T152 North Haverhill 69kV 69 140 Coal Withdrawn
N12 North Haverhill 69 75 Coal In Service