Substation Scout

Farmville - Moran DP substation interconnection queue

0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).

2 PJM queue filings name Farmville - Moran DP as the point of interconnection, all in Prince Edward County, VA.

Target commercial operation date as filed: Sep 2026 (2 filings).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
AI1-145 Farmville - Moran DP 115 kV 115 75 Solar Withdrawn Sep 2026
AI1-146 Farmville - Moran DP 115 kV 115 20 Battery Withdrawn Sep 2026

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

Other PJM queue substations in Prince Edward County, VA

All 20 PJM queue filings in Prince Edward County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first