Eddystone substation interconnection queue
2 active projects totalling 528 MW in the PJM queue, plus 3 with terminal status (shown greyed).
2active projects
528active MW
5total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| U1-013 | Eddystone | n/r | 630 | Gas | Withdrawn |
| AA2-110 | Eddystone 230kV | 230 | 550 | Gas | Withdrawn |
| A19 | Liberty (Eddy) | 230 | 521 | Gas | In Service |
| M27 | Eddystone | 138 | 7 | Coal | In Service |
| AB1-073 | Eddystone 138kV | 138 | 0 | Battery | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.