Substation Scout

Delco Tap substation interconnection queue

0 active projects totalling 0 MW in the PJM queue, plus 2 with terminal status (shown greyed).

0active projects
0active MW
2total filed
Queue IDProjectkVMWResourceStatus
T38 Delco Tap 230kV 230 900 Gas Withdrawn
E19 Delco Tap 230kV 230 330 Gas Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.