Culpeper substation interconnection queue
0 active projects totalling 0 MW in the PJM queue, plus 8 with terminal status (shown greyed).
0active projects
0active MW
8total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| AC2-113 | Culpeper North | 35 | 13.3 | Solar | Withdrawn |
| AB2-052 | Culpeper 34.5kV | 34.5 | 13 | Solar | Withdrawn |
| AG1-344 | Culpeper 34.5 kV | 34.5 | 12 | Solar | Withdrawn |
| AB2-023 | Culpeper 34.5kV | 34.5 | 9.7 | Solar | Withdrawn |
| AB1-152 | Stevensburg Solar | 34.5 | 7.6 | Solar | Withdrawn |
| AD1-049 | Culpeper 34.5 kV | 34.5 | 6.3 | Solar | Withdrawn |
| AF2-401 | Stevensburg Road Solar | 34.5 | 3.5 | Solar | Withdrawn |
| AB2-053 | Culpeper 34.5kV | 34.5 | 0 | Solar | Withdrawn |
Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.