Remington-Gordonsville substation interconnection queue
0 active projects totaling 0 MW in the PJM queue, plus 2 with terminal status (shown grayed).
2 PJM queue filings name Remington-Gordonsville as the point of interconnection, all in Culpeper County, VA.
Target commercial operation dates as filed run from Oct 2024 to May 2027 (2 filings).
Transmission owner as filed: Dominion (1 filing).
| Queue ID | Project | kV | MW | Resource | Status | Target COD |
|---|---|---|---|---|---|---|
| AE1-153 | Maroon Solar | 230 | 89.4 | Solar | Withdrawn | May 2027 |
| AG1-538 | Remington-Gordonsville 230 kV | 230 | 32 | Battery | Withdrawn | Oct 2024 |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.
Tracked changes at this substation
2 changes to filings at this point of interconnection, observed between weekly snapshots of the PJM queue. For a capacity revision MW is the change, not the new total.
| Detected | Queue ID | Change | MW | Status was → now |
|---|---|---|---|---|
| 2026-11-02 | AE1-153 | Status change | n/a | Pending Termination → Withdrawn |
| 2026-09-23 | AE1-153 | Terminal status | 89.4 | Engineering and Procurement → Pending Termination |
Same name on other Substation Scout pages
Other sources that print a substation named “Remington-Gordonsville” in VA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each.
- Remington- Gordonsville: PJM interconnection queue (VA)
Other PJM queue substations in Culpeper County, VA
- Brandy - McDevitt: 2 active, 415 MW of 2 filed
- Culpeper: none active of 8 filed
- Gordonsville-Remington: none active of 2 filed
- Mitchell-Mountain Run: none active of 2 filed
- Mountain Run-Mitchell: none active of 2 filed
- Remington- Gordonsville: none active of 2 filed