Substation Scout

Cloverdale substation interconnection queue

1 active project totaling 250 MW in the PJM queue, plus 1 with terminal status (shown grayed).

2 PJM queue filings name Cloverdale as the point of interconnection, all in Botetourt County, VA.

Target commercial operation dates as filed run from Oct 2023 to Apr 2030 (2 filings). 1 active filing targets a date after November 27, 2026.

Transmission owner as filed: AEP (1 filing).

1active projects
250active MW
2total filed
Queue IDProjectkVMWResourceStatusTarget COD
C01-2044 Cloverdale 345kV 345 kV 345 250 Battery Active Apr 2030
AG1-155 Cloverdale 34.5 kV 34.5 8 Battery Withdrawn Oct 2023

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with PJM before relying on these figures.

PJM planning mentions

A substation with the same name is named in PJM transmission planning materials: Cloverdale (AEP, 3 mentions).

Same name and transmission owner. Matched on name and transmission owner: the utility that presented this substation in PJM planning materials is the transmission owner recorded on the queue filings at a substation of the same name. Not verified as the same facility.

Same name on other Substation Scout pages

Other sources that print a substation named “Cloverdale” in VA. They are matched by name and state only, so a page listed here may describe a different substation with the same name. Check the location and utility on each. Where a PJM planning record prints no state, the match is by name within the states the utility zone serves, which is weaker.

Other PJM queue substations in Botetourt County, VA

All 13 PJM queue filings in Botetourt County, VA.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.