Substation Scout

Botetourt, VA interconnection queue

4 active projects totalling 342.1 MW in the PJM queue, plus 9 with terminal status (shown greyed).

4active projects
342.1active MW
13total filed
Queue IDProjectkVMWResourceStatus
C01-2044 Cloverdale 345kV 345 kV 345 250 Battery Active
AG1-240 Trinity 69 kV 69 90 Battery Withdrawn
AI2-231A Cloverdale-Burlington Height 138 kV 138 60 Battery Withdrawn
C01-1625 Bonsack 138 kV 138 50 Battery Active
AG1-136 Gateway Grid 138 40 Battery Withdrawn
AI2-225 Lexington-Low Moor 230kV 230 32 Wind Withdrawn
C01-1232 Rocky Forge 230 kV 230 32 Wind Active
U4-026 Rocky Ford WF 230 13 Wind Withdrawn
AC1-227 Low Moor-Lexington 230kV 230 12 Wind Withdrawn
AA1-038 Rocky Forge Wind 230 10.1 Wind Under Construction
AC2-003 Not reported n/r 10 Wind Withdrawn
AG1-155 Cloverdale 34.5 kV 34.5 8 Battery Withdrawn
T132 Cloverdale-Lexington 500kV 500 0 Not reported Withdrawn

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with PJM before relying on these figures.