Hilltopper Wind Farm (X2-022) is listed in the PJM interconnection queue as a wind request filed at 0 MW (a net change or energy-only filing) in Logan County, IL. The filing names Brokaw-Lanesville as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of May 31, 2019.
| Queue ID | X2-022 |
|---|---|
| Project name | Hilltopper Wind Farm |
| Status (as published) | In Service |
| Substation | Brokaw-Lanesville |
| Point of interconnection | Brokaw-Lanesville |
| County | Logan |
| State | IL |
| Voltage | Not reported |
| Capacity | 0 MW (0 MW as filed — net change or energy-only) |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2019-05-31 |
| Source dataset | serial |
Same substation and county
Brokaw-Lanesville substation: 6 requests in the PJM queue, 5 active totaling 52.8 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| AD1-148 | HillTopper Wind Farm | 36.3 | Wind | In Service |
| AF2-305 | Alta Farms II | 9.2 | Wind | In Service |
| AG1-398 | Alta Farms II | 7.3 | Wind | In Service |
| W2-048 | Hilltopper Wind, LLC | 0 | Wind | In Service |
| U4-037 | Brokaw-Lanesville 345kV | 26 | Wind | Withdrawn |
Logan, IL: 14 requests in the PJM queue, 6 active totaling 156 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 187.5 |
| MW capacity | 0 |
| MFO | 250 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.