Substation Scout

HillTopper Wind Farm

PJM queue ID AD1-148

HillTopper Wind Farm (AD1-148) is listed in the PJM interconnection queue as a 36.3 MW wind project in Logan County, IL. The filing names Brokaw-Lanesville as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of September 1, 2022.

Queue IDAD1-148
Project nameHillTopper Wind Farm
Status (as published)In Service
SubstationBrokaw-Lanesville
Point of interconnectionBrokaw-Lanesville
CountyLogan
StateIL
VoltageNot reported
Capacity36.3 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2022-09-01
Source datasetserial

Same substation and county

Brokaw-Lanesville substation: 6 requests in the PJM queue, 5 active totaling 52.8 MW.

Queue IDProjectMWResourceStatus
AF2-305Alta Farms II9.2WindIn Service
AG1-398Alta Farms II7.3WindIn Service
W2-048Hilltopper Wind, LLC0WindIn Service
X2-022Hilltopper Wind Farm0WindIn Service
U4-037Brokaw-Lanesville 345kV26WindWithdrawn

Logan, IL: 14 requests in the PJM queue, 6 active totaling 156 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy0
MW capacity36.3
MFO185

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.