Paradise SP (U4-036) is listed in the PJM interconnection queue as a 1.9 MW solar project in Gloucester County, NJ. The filing names Gloucester as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of January 4, 2011.
| Queue ID | U4-036 |
|---|---|
| Project name | Paradise SP |
| Status (as published) | In Service |
| Substation | Gloucester |
| Point of interconnection | Gloucester 26.4kV |
| County | Gloucester |
| State | NJ |
| Voltage | 26.4 kV |
| Capacity | 1.9 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Target commercial operation | 2011-01-04 |
| Source dataset | serial |
Same substation and county
Gloucester substation: 8 requests in the PJM queue, 3 active totaling 7.1 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| Z2-062 | Camden County Energy Recovery Associates | 3 | Gas | In Service |
| AC1-010 | National Park NJ | 2.2 | Solar | In Service |
| R58 | Camden Cogen Tech | 55 | Gas | Withdrawn |
| AG1-263 | Gloucester 230 kV | 8 | Battery | Withdrawn |
| W2-031 | Gloucester 26kV | 3.2 | Solar | Withdrawn |
| V4-013 | Gloucester 26kV | 2 | Solar | Withdrawn |
| AE2-066 | Gloucester 13 kV | 1.9 | Solar | Withdrawn |
Gloucester, NJ: 88 requests in the PJM queue, 22 active totaling 1,788.6 MW.
A substation with the same name is named in PJM transmission planning materials: Gloucester (PSEG, 6 mentions).
Same name and state (weaker). Matched on name and state: the utility that presented this substation operates in one state, and every queue filing at a substation of the same name is in that state. No transmission owner is recorded on those filings, so this is a weaker match than one on owner. Not verified as the same facility.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Project type | Generation Interconnection |
|---|---|
| MW energy | 5.1 |
| MW capacity | 1.9 |
| MFO | 5.1 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.