Substation Scout

Green River Wind Farm Phase 2

PJM queue ID O29

Queue IDO29
Project nameGreen River Wind Farm Phase 2
Status (as published)In Service
SubstationNormandy
Point of interconnectionNormandy 138kV
CountyLee
StateIL
Voltage138 kV
Capacity45 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2019-10-30
Source datasetserial

Additional filed fields

Project TypeGeneration Interconnection
Mw Energy225
Mw Capacity45
Mfo225

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.