Green River Wind Farm Phase 2

PJM queue ID O29

Green River Wind Farm Phase 2 (O29) is listed in the PJM interconnection queue as a 45 MW wind project in Lee County, IL. The filing names Normandy as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of October 30, 2019.

Queue IDO29
Project nameGreen River Wind Farm Phase 2
Status (as published)In Service
SubstationNormandy
Point of interconnectionNormandy 138kV
CountyLee
StateIL
Voltage138 kV
Capacity45 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2019-10-30
Source datasetserial

Same substation and county

Normandy substation: 5 requests in the PJM queue, 3 active totaling 127.4 MW.

Queue IDProjectMWResourceStatus
O09Walnut Ridge Wind, LLC42.4WindIn Service
C01-1622Normandy 138 kV40WindActive
P37Normandy 138kV28WindWithdrawn
AD2-041Normandy11.6SolarWithdrawn

Lee, IL: 106 requests in the PJM queue, 30 active totaling 2,565.3 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy225
MW capacity45
MFO225

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.