Walnut Ridge Wind, LLC (O09) is listed in the PJM interconnection queue as a 42.4 MW wind project in Lee County, IL. The filing names Normandy as its point of interconnection. PJM lists its status as “In Service”, with a target commercial operation date of October 15, 2018.

Queue IDO09
Project nameWalnut Ridge Wind, LLC
Status (as published)In Service
SubstationNormandy
Point of interconnectionNormandy
CountyLee
StateIL
VoltageNot reported
Capacity42.4 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Target commercial operation2018-10-15
Source datasetserial

Same substation and county

Normandy substation: 5 requests in the PJM queue, 3 active totaling 127.4 MW.

Queue IDProjectMWResourceStatus
O29Green River Wind Farm Phase 245WindIn Service
C01-1622Normandy 138 kV40WindActive
P37Normandy 138kV28WindWithdrawn
AD2-041Normandy11.6SolarWithdrawn

Lee, IL: 106 requests in the PJM queue, 30 active totaling 2,565.3 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

Project typeGeneration Interconnection
MW energy212
MW capacity42.4
MFO212

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.