Normandy 138 kV

PJM queue ID C01-1622

Queue IDC01-1622
Project nameNormandy 138 kV
Status (as published)Active
SubstationNormandy
Point of interconnectionNormandy 138 kV
CountyWhiteside
StateIL
Voltage138 kV
Capacity40 MW
Resource (as published)Wind
Resource categoryWind (normalised for filtering)
Target commercial operation2027-12-01
Source datasetcycle

Additional filed fields

DeveloperGreen River Wind Farm Phase 1, LLC
Transmission OwnerComEd
Project TypeGeneration Interconnection
CycleC01
StagePhase 1
Mw Energy0.0
Mw Capacity40.0
Mfo194.25
Submitted Date4/25/2026
Last Updated6/24/2026