Normandy 138 kV
PJM queue ID C01-1622
Normandy 138 kV (C01-1622) is listed in the PJM interconnection queue as a 40 MW wind project in Whiteside County, IL. The filing names Normandy as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 1, 2027.
| Queue ID | C01-1622 |
|---|---|
| Project name | Normandy 138 kV |
| Status (as published) | Active |
| Substation | Normandy |
| Point of interconnection | Normandy 138 kV |
| County | Whiteside |
| State | IL |
| Voltage | 138 kV |
| Capacity | 40 MW |
| Resource (as published) | Wind |
| Resource category | Wind (normalized for filtering) |
| Target commercial operation | 2027-12-01 |
| Source dataset | cycle |
Same substation and county
Normandy substation: 5 requests in the PJM queue, 3 active totaling 127.4 MW.
| Queue ID | Project | MW | Resource | Status |
|---|---|---|---|---|
| O29 | Green River Wind Farm Phase 2 | 45 | Wind | In Service |
| O09 | Walnut Ridge Wind, LLC | 42.4 | Wind | In Service |
| P37 | Normandy 138kV | 28 | Wind | Withdrawn |
| AD2-041 | Normandy | 11.6 | Solar | Withdrawn |
Whiteside, IL: 13 requests in the PJM queue, 5 active totaling 246.6 MW.
Tracked changes
No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →
Additional filed fields
| Developer | Green River Wind Farm Phase 1, LLC |
|---|---|
| Transmission owner | ComEd |
| Project type | Generation Interconnection |
| Cycle | C01 |
| Stage | Phase 1 |
| MW energy | 0.0 |
| MW capacity | 40.0 |
| MFO | 194.25 |
| Submitted date | 4/25/2026 |
| Last updated | 6/24/2026 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.