PJM queue ID C01-1656

Elk 138 kV (C01-1656) is listed in the PJM interconnection queue as a 47.5 MW solar project in Vinton County, OH. The filing names Elk as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of April 24, 2028.

Queue IDC01-1656
Project nameElk 138 kV
Status (as published)Active
SubstationElk
Point of interconnectionElk 138 kV
CountyVinton
StateOH
Voltage138 kV
Capacity47.5 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2028-04-24
Source datasetcycle

Same substation and county

Elk substation: 4 requests in the PJM queue, 3 active totaling 137 MW.

Queue IDProjectMWResourceStatus
AC1-194Vinton Solar47.5SolarSuspended
AE1-093Vinton Energy Storage42BatterySuspended
AI2-157Elk 138 kV47.5SolarWithdrawn

Vinton, OH: 8 requests in the PJM queue, 6 active totaling 334.6 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperVinton Solar Energy LLC
Transmission ownerAEP
Project typeGeneration Interconnection
CycleC01
StagePhase 1
MW energy0.0
MW capacity47.5
MFO125.0
Submitted date4/27/2026
Last updated6/24/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first