Jetersville-Ponton 115 kV

PJM queue ID AH1-280

Jetersville-Ponton 115 kV (AH1-280) is listed in the PJM interconnection queue as a 12 MW solar project in Amelia County, VA. The filing names Jetersville-Ponton as its point of interconnection. PJM lists its status as “Active”, with a target commercial operation date of December 31, 2028.

Queue IDAH1-280
Project nameJetersville-Ponton 115 kV
Status (as published)Active
SubstationJetersville-Ponton
Point of interconnectionJetersville-Ponton 115 kV
CountyAmelia
StateVA
Voltage115 kV
Capacity12 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Target commercial operation2028-12-31
Source datasetcycle

Same substation and county

Jetersville-Ponton substation: 7 requests in the PJM queue, 5 active totaling 158.5 MW.

Queue IDProjectMWResourceStatus
C01-2000Jetersville-Ponton 115 kV100BatteryActive
AF1-294Amelia Energy Facility22.2SolarEP
AF2-115Amelia Energy Facility13.5SolarEP
AG1-021Amelia Energy Facility10.8SolarEP
AG1-048Jetersville-Ponton 115 kV52.5SolarWithdrawn
C01-1347Jetersville-Ponton 115 kV12SolarWithdrawn

Amelia, VA: 8 requests in the PJM queue, 6 active totaling 160.4 MW.

Tracked changes

No changes to this filing observed since PJM tracking began on August 27, 2026. Full change log →

Additional filed fields

DeveloperAmelia Energy Facility, LLC
Transmission ownerDominion
Project typeGeneration Interconnection
CycleTC2
StagePhase 3
MW energy20.0
MW capacity12.0
MFO106.0
Submitted date9/9/2021
Last updated8/18/2026

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first